Sign In  |  Register  |  About Corte Madera  |  Contact Us

Corte Madera, CA
September 01, 2020 10:27am
7-Day Forecast | Traffic
  • Search Hotels in Corte Madera

  • CHECK-IN:
  • CHECK-OUT:
  • ROOMS:

AngloGold Ashanti Delivers Steady Start to 2024; Gold Production1 Up +2% y-o-y; Gold Production Guidance Reconfirmed and Obuasi on Track to Achieve FY 2024 Forecast Gold Production

AngloGold Ashanti plc (“AngloGold Ashanti”, “AGA” or the “Company”) today reported a 2% year-on-year increase in first quarter gold production1, in line with its plans and despite the previously reported impact of rains and flooding in Western Australia on gold production which contributed to a drop of about 15,000oz in production in the first quarter relative to the previous quarter. The Company reconfirmed its 2024 full-year gold production guidance and its 2024 annual gold production forecast for Obuasi in Ghana, which continues its ramp-up.

“This is a good start to the year, with another strong safety result and a good overall performance from the portfolio,” said Chief Executive Officer Alberto Calderon. “We’re seeing greater consistency from most of our operations; in Brazil, both sites have shown significantly better performance, with greater production control and stability. Geita and Kibali were strong again, and Obuasi’s ramp-up remains on track.”

Denver-headquartered AngloGold Ashanti continues to take steps to close the value gap that exists with its North American peers by improving safety, relative cost performance and cash conversion, while increasing the life of its key mines and prioritising successful development of major projects.

The Company’s Total Recordable Injury Frequency Rate (“TRIFR”) was 1.08 injuries per million hours worked during the first quarter of 2024, compared to the most recent average (2022) of 2.66 for members of the International Council on Metals & Minerals (“ICMM”). No fatalities were recorded at mines operated by the Company in the first three months of 2024, for the eleventh consecutive quarter.

Gold production1 was 2% higher year-on-year at 581,000oz for the first quarter of 2024, compared to 572,000oz for the first quarter of 2023, driven mainly by higher recovered grades, and partly offset by lower tonnes processed. Strong improvements in gold production versus the first quarter of last year were recorded at Cuiabá (AGA Mineração) (+55%) and Serra Grande (+40%), where initiatives have been taken to improve overall performance, as well as at Kibali (+19%) and at Geita (+16%).

This increase in gold production was partly offset by lower gold production at Siguiri (-35%), where carbonaceous ore in the Bidini pit resulted in poor recoveries, and at Tropicana (-17%), where severe flooding, caused by a tropical cyclone, inundated underground and open pit mining areas as well as access roads to the remote site. Both mines have since recovered to normalised gold production levels. Sunrise Dam (-8%) also suffered from the heavy rainfall in Western Australia, albeit to a lesser extent than Tropicana, while gold production at Cerro Vanguardia (-7%) was lower due to a planned plant stoppage.

At Obuasi, gold production was 54,000oz, in line with the mine plan, as mining occurred in lower-grade areas. Obuasi’s underground ore tonnes treated averaged 91,000t/pm for the first three months of 2024. Underground tonnes treated and grade are expected to increase in the second half of 2024, supported by additional development. The mine remains on track to produce an anticipated 275,000oz – 320,000oz of gold in 2024.

As previously reported, gold production at Tropicana was impacted by heavy rains and flooding during the month of March. The area in which the Tropicana gold mine is located received 312mm of rain in a 72-hour period from 9 March, almost 40% higher than its average annual rainfall. The subsequent flooding interrupted power supply to the processing plant and required mining operations to be suspended. Since the flooding, remedial work to recommence operations was successfully completed and mining and processing has since restarted. Whilst gold production was impacted in the first quarter of 2024, and consequently for the first half of 2024, the Company expects to recover a significant portion of these production losses in the second half of 2024.

The Company provided gold production guidance for 2024 in February, which remains unchanged. Gold production is again expected to be second half weighted, with fourth quarter gold production expected to be the strongest quarter this year.

1 Excluding the Córrego do Sítio (“CdS”) operation which was placed on care and maintenance in August 2023.

 

 

Quarter

Quarter

Quarter

Year

 

 

ended

ended

ended

ended

 

 

Mar

Dec

Mar

Dec

 

 

2024

2023

2023

2023

Gold produced (1)

 

 

 

 

 

– Subsidiaries (2) (3)

oz (000)

505

632

508

2,250

– Joint ventures

oz (000)

76

93

64

343

– Group (2) (3)

oz (000)

581

725

572

2,593

Tonnes treated

 

 

 

 

 

Open-pit

 

 

 

 

 

– Subsidiaries

tonnes (000)

5,608

6,741

6,065

25,094

– Joint ventures

tonnes (000)

509

478

538

2,065

– Group

tonnes (000)

6,117

7,219

6,603

27,159

Underground

 

 

 

 

 

– Subsidiaries

tonnes (000)

2,216

2,596

2,104

9,511

– Joint ventures

tonnes (000)

416

433

342

1,635

– Group

tonnes (000)

2,632

3,029

2,446

11,146

Other

 

 

 

 

 

– Subsidiaries

tonnes (000)

726

859

635

3,007

– Joint ventures

tonnes (000)

– Group

tonnes (000)

726

859

635

3,007

Total

 

 

 

 

 

– Subsidiaries

tonnes (000)

8,550

10,196

8,804

37,612

– Joint ventures

tonnes (000)

925

911

880

3,700

– Group

tonnes (000)

9,475

11,107

9,684

41,312

Recovered grade

 

 

 

 

 

Open-pit

 

 

 

 

 

– Subsidiaries

g/tonne

1.03

1.30

1.18

1.23

– Joint ventures

g/tonne

0.97

1.72

1.32

1.58

– Group

g/tonne

1.03

1.33

1.19

1.25

Underground

 

 

 

 

 

– Subsidiaries

g/tonne

3.72

3.51

3.63

3.48

– Joint ventures

g/tonne

4.48

4.76

3.71

4.54

– Group

g/tonne

3.84

3.69

3.64

3.63

Other

 

 

 

 

 

– Subsidiaries

g/tonne

2.32

2.05

1.58

2.05

– Joint ventures

g/tonne

– Group

g/tonne

2.32

2.05

1.58

2.05

Total

 

 

 

 

 

– Subsidiaries

g/tonne

1.84

1.93

1.80

1.86

– Joint ventures

g/tonne

2.55

3.17

2.25

2.89

– Group

g/tonne

1.91

2.03

1.84

1.95

(1)

 

On an attributable basis.

(2)

 

Adjusted to exclude the Córrego do Sítio (CdS) operation that was placed on care and maintenance in August 2023. CdS produced nil koz, 2koz and 12koz for the quarters ended 31 March 2024, 31 December 2023 and 31 March 2023, respectively. CdS produced 42koz for the year ended 31 December 2023.

(3)

 

Includes gold concentrate from the Cuiabá mine sold to third parties.

Rounding of figures may result in computational discrepancies

OPERATING HIGHLIGHTS

In the Africa region – subsidiaries, gold production (on an attributable basis) was 271,000oz for the quarter ended 31 March 2024, compared to 284,000oz for the quarter ended 31 March 2023. In the Africa region – joint ventures, gold production (on an attributable basis) was 76,000oz for the quarter ended 31 March 2024, compared to 64,000oz for the quarter ended 31 March 2023.

In Ghana, at Iduapriem, gold production was 62,000oz for the quarter ended 31 March 2024, compared to 63,000oz for the same period last year, mainly due to a marginal decrease in recovered grade, partly offset by higher tonnes processed.

At Obuasi, gold production was 54,000oz for the quarter ended 31 March 2024, in line with the mine plan, compared to 60,000oz for the same period last year. Total ore tonnes mined and treated were 18% higher when compared with the first quarter of 2023, while grade was 24% lower, in line with the mine plan. During the first quarter of 2024, underground ore tonnes treated averaged 91kt/pm, supported by additional development. The site is contending with intermittent power disruptions from the public utility. Obuasi is forecast to produce between 275,000oz and 320,000oz of gold in 2024 and between 325,000oz and 375,000oz of gold in 2025, as it continues its ramp-up to steady state production.

In Guinea, at Siguiri, gold production (on an attributable basis) was 41,000oz for the quarter ended 31 March 2024, compared to 63,000oz for the same period last year. Gold production was lower year-on-year mainly due to poor equipment availability, lower feed grades and a significant decline in metallurgical recoveries in the plant, associated with highly carbonaceous ore feed from parts of the Bidini pit. The mine has taken delivery of a new excavator in April 2024 and subsequently prioritised ore from alternative mining areas, which has assisted a recovery in gold production rates after the quarter-end.

In Tanzania, at Geita, gold production was 114,000oz for the quarter ended 31 March 2024, compared to 98,000oz for the same period last year. Gold production was higher year-on-year mainly due to higher total recovered grade of 2.85g/t, compared to total recovered grade of 2.70g/t in the same period in 2023. Underground treated material increased mainly due to a stronger underground performance, partly offset by a relatively weaker open pit performance. A strong end to 2023 from the underground mining areas enabled additions to ore stockpiles, supporting the increased feed ratio from underground during the first quarter of 2024. In addition, tonnes treated were higher in the quarter ended 31 March 2024 given the impact of the SAG mill shutdown to replace the girth gear in the same period last year.

In the DRC, at Kibali, gold production (on an attributable basis) was 76,000oz for the quarter ended 31 March 2024, compared to 64,000oz for the same period last year. Gold production was higher year-on-year mainly due to higher recovered grades resulting from a higher proportion of underground ore tonnes treated at a higher feed grade as a result of increased underground efficiency in the quarter ended 31 March 2024 as compared to the same period in 2023 during which time the mine was converting to underground multi-lite mining.

In the Americas, gold production (excluding CdS) was 125,000oz of gold (on an attributable basis) for the quarter ended 31 March 2024, compared to 99,000oz for the quarter ended 31 March 2023.

Brazil delivered a significant turnaround following the operational issues encountered in 2023, with improvements on most production metrics across both operations. At Cuiabá (AGA Mineração), gold production was 65,000oz for the quarter ended 31 March 2024, compared to 42,000oz for the same period last year. Gold production was higher year-on-year mainly due to higher tonnes processed and higher recovered grades. Cuiabá’s gold production comprised 21,000oz of gravimetric gold and 44,000oz of gold-in-concentrate.

At Serra Grande, gold production was 21,000oz for the quarter ended 31 March 2024, compared to 15,000oz for the same period last year. Gold production was higher year-on-year mainly due to higher recovered grades, partly offset by lower tonnes processed.

In Argentina, at Cerro Vanguardia, gold production (on an attributable basis) was 39,000oz for the quarter ended 31 March 2024, compared to 42,000oz for the same period last year. Gold production was lower year-on-year mainly due to lower plant throughput as a result of a planned plant stoppage that was carried out in March 2024, partly offset by the placement of higher heap leach tonnes due to operational efficiencies.

In Australia, gold production was 109,000oz of gold (on an attributable basis) for the quarter ended 31 March 2024, compared to 125,000oz for the quarter ended 31 March 2023.

At Sunrise Dam, gold production was 56,000oz for the quarter ended 31 March 2024, compared to 61,000oz for the same period last year. Gold production was lower year-on-year mainly due to lower recovered grades, partly offset by higher tonnes processed.

At Tropicana, gold production (on an attributable basis) was 53,000oz for the quarter ended 31 March 2024, compared to 64,000oz for the same period last year. Gold production was lower year-on-year mainly due to lower tonnes processed. As noted above, gold production was impacted by heavy rains and flooding during the month of March. The area in which the Tropicana gold mine is located received 312mm of rain in a 72-hour period from 9 March, almost 40% higher than its average annual rainfall. The subsequent flooding interrupted power supply to the processing plant and required mining operations to be temporarily suspended. Since the flooding, remedial work to recommence operations was successfully completed and mining and processing has since restarted. The impact of the rainfall event at Tropicana is expected to continue into the second quarter of 2024 as water continues to be pumped out of the Havana 5 pit, which was scheduled to be the main source of open pit ore in the first half of 2024. The operation expects to process proportionally more ore from stockpiles whilst ore from Havana 5 has been deferred into the second half of 2024. The impact on gold production at Tropicana during the first half of 2024 is expected to be partly offset in the second half of the year, as higher-grade ore from the Havana 5 pit becomes available and the Havana 4 pit ramps up production.

GUIDANCE

The Company provided gold production guidance for 2024 in February, which remains unchanged. Gold production is again expected to be second half weighted, with fourth quarter gold production expected to be the strongest quarter this year.

 

2024

 

Gold Production (000oz)

 

Gold Production

– Subsidiaries

2,270 - 2,430

– Joint ventures

320 - 360

– Group

2,590 - 2,790

Estimates assume neither operational or labour interruptions (including any further delays in the ramp-up of the Obuasi redevelopment project), or power disruptions, nor further changes to asset portfolio and/or operating mines. Other unknown or unpredictable factors, or factors outside the Company’s control, could also have material adverse effects on AngloGold Ashanti’s future gold production and no assurance can be given that any expectations expressed by AngloGold Ashanti will prove to have been correct. Measures taken at AngloGold Ashanti’s operations together with AngloGold Ashanti’s business continuity plans aim to enable its operations to deliver in line with its gold production targets. Actual gold production could differ from guidance and any deviations may be significant. Please refer to the Risk Factors section in AngloGold Ashanti’s annual report on Form 20-F for the year ended 31 December 2023 filed with the United States Securities and Exchange Commission (“SEC”).

SAFETY UPDATE

The Company recorded a fatality-free first quarter of 2024 at the mines it operates. The TRIFR, the broadest measure of workplace safety, was 1.08 injuries per million hours worked for the first quarter of 2024 and 0.85 injuries per million hours worked for the fourth quarter of 2023. By comparison, the most recent ICMM average (2022) amounts to 2.66 injuries per million hours worked.

UPDATE ON CAPITAL PROJECTS

Obuasi

UHDF trial update

The underhand drift and fill (“UHDF”) mining method trial in Block 8 Lower progressed well during the first quarter of 2024. The UHDF trial aims to test the mining method to ensure it can be used safely and effectively to mine high-grade ore in areas with poor ground conditions associated with weak graphitic shears and increasing mining depth.

Milestones achieved in the first quarter of 2024:

  • Developed alongside paste-filled 3,300 level drive to expose and test paste strength.
  • Confirmed in-situ paste strength in this parallel drive, and installed ground support.
  • Trialed slag-based binders to increase backfill strength and reduce curing times.
  • Paste backfill commenced on 24 April 2024 and completed successfully in single pour.
  • Paste curing successfully achieved required strength within 14 days.

Next steps:

  • Development beneath paste-fill scheduled to commence on 9 May 2024.
  • Annualised production rate of 360,000oz is expected in the third quarter of 2024.

Phase 3

Phase 3 of the Obuasi redevelopment project relates primarily to capital expenditure required to refurbish and return to service the KMS shaft and associated infrastructure. This infrastructure project, which provides direct access to the high-grade Block 11 and other underground mining areas and augments current underground materials handling capacity, is expected to be completed by the end of 2024 after being extended during 2023 when mud, encountered on 5,000 and 5,100 levels, had to be cleared.

Phase 3 achieved the following milestones in the first quarter of 2024:

  • Commissioned the first 100 l/sec pumping system of the three pumping systems planned.
  • Completed reaming of the 945m vent raise marking a significant achievement for a raise bore.
  • Completed the man winder upgrades to a modern thyristor controlled winder.
  • Re-entered 50 level to complete the final works ahead of starting the installation of the lower shaft loading system.

The next key project milestones include:

  • Completion of two new ore passes between upper mine and the rail transport level.
  • Completion of new pump stations and pump columns allowing 300 l/sec shaft pumping.
  • Installation and commissioning of the new vent shaft.
  • Commissioning the rail system.
  • Clearing mud on 5,100 level and shaft bottom.

Tropicana

The Havana underground feasibility study commenced in the third quarter of 2023 and is expected to continue into the first half of 2024. A final investment decision is expected to be made in 2024. Development of a link drive began during the first quarter of 2024 to provide access to additional drill areas between Tropicana and Havana. The link drive is expected to ultimately link up with the Havana underground.

Tropicana ESG renewables

The Tropicana renewable energy project is on track with the delivery and installation of the wind turbines and solar plant expected to commence in the second quarter of 2024. The renewable energy project is expected to be commissioned in the first quarter of 2025 and, upon completion, is expected to reduce greenhouse gas (“GHG”) emissions at Tropicana by 65,000 tonnes per annum on average over the 10-year life of the power purchase agreement.

North Bullfrog Project (“NBP”)

AngloGold Ashanti’s board of directors approved the feasibility study for the NBP to proceed into detailed engineering. The NBP received spend approval from AngloGold Ashanti’s Management Investment Committee to pursue detailed engineering during 2024. Permitting processes are underway for the NBP. In early April 2024, the U.S. Bureau of Land Management (“BLM”) published the Notice of Intent to Prepare an Environmental Impact Statement in the Federal Register.

Good progress was made during the first quarter of 2024, with the hiring of the owner’s engineering team largely completed along with the completion of the front-end engineering and design of the mill facility, and earthworks for the heavy mobile equipment assembly yard. The NBP remains on schedule, contingent on receipt of the requisite permits, to commence anticipated gold production in 2026.

Merlin

Successful completion of the concept study at the end of 2023 allowed the Merlin project to proceed to the next stage gate of the pre- feasibility study (“PFS”). The PFS programme is expected to be performed through the middle of 2025 with a focus on an extensive drilling programme and further optimisation of development options considered as part of the framing review in the first half of 2024.

Quebradona

Following the decision of Colombia’s national environmental agency (“ANLA”) in November 2021 to archive the Company’s environmental licence application related to the Quebradona Project, and the confirmation of such decision in April 2022, AngloGold Ashanti has been working to complete the data acquisition required by ANLA. AngloGold Ashanti is in the process of preparing a new Environmental Impact Assessment in connection with its environmental licence application for the project, which is currently expected to be submitted to ANLA in 2027. In addition, an optimised feasibility study is currently underway to implement improvements in water management, operational flexibility, maintainability, and constructability.

CORPORATE UPDATE

Proposed Tarkwa / Iduapriem Joint Venture

In March 2023, AngloGold Ashanti announced the proposed joint venture between the Iduapriem mine and Gold Fields neighbouring Tarkwa mine in Ghana, that has the potential to create Africa’s largest gold mine. In addition to leveraging operating efficiencies to unlock higher grades and enabling an extension of life to at least 18 years, the proposed joint venture is expected to create compelling shared value for all stakeholders.

Since the announcement, AngloGold Ashanti and Gold Fields have been in ongoing engagement with the Government of Ghana with respect to the proposed transaction. While significant progress has been made, agreement has not yet been reached. The Company will continue to keep the market updated on any significant developments in this regard.

AngloGold Ashanti makes a strategic investment in G2 Goldfields Inc.

On 19 January 2024, AngloGold Ashanti completed its acquisition of an 11.7% interest in G2 Goldfields Inc., a Canadian gold mining company with exploration properties in Guyana, South America, for a consideration of approximately CAD $22.1m.

Appointment of Group Company Secretary

The Company has appointed Ms. Catherine Stead as Group Company Secretary of AngloGold Ashanti plc with effect from 1 April 2024. The mandate of Ms. Helen Grantham as Interim Group Company Secretary expired at the end of March 2024.

Reporting Update

AngloGold Ashanti qualifies as a foreign private issuer (“FPI”) in the United States for purposes of the US Securities Exchange Act of 1934, as amended (the “US Exchange Act”), is filing annual reports on Form 20-F and is furnishing current reports on Form 6-K with the SEC as the SEC has prescribed for FPIs. AngloGold Ashanti had previously announced that it was planning to voluntarily file annual reports on Form 10-K, quarterly reports on Form 10-Q and current reports on Form 8-K with the SEC, that is, the forms that the SEC has prescribed for more comprehensive reporting by US domestic issuers, instead of filing on the reporting forms available to FPIs, starting with the 10-Q filing for the second quarter of 2024. AngloGold Ashanti remains committed to voluntarily transition to reporting on US domestic forms, but now plans to do so at a later date which will be communicated to the market in advance of that transition. Until it commences voluntary reporting on US domestic forms, AngloGold Ashanti will provide full financial and operational updates, including unaudited condensed consolidated interim financial statements, on a quarterly basis, which will be furnished on current reports on Form 6-K with the SEC.

Operations at a glance

for the quarters ended 31 March 2024, 31 December 2023 and 31 March 2023

 

 

Gold production

oz (000)

 

Open-pit treated

000 tonnes

Underground milled /

treated

000 tonnes

 

Other milled / treated

000 tonnes

Open-pit recovered

grade

g/tonne

Underground recovered

grade

g/tonne

 

Other recovered grade

g/tonne

 

Total recovered grade

g/tonne

Mar-24

Dec-23

Mar-23

Mar-24

Dec-23

Mar-23

Mar-24

Dec-23

Mar-23

Mar-24

Dec-23

Mar-23

Mar-24

Dec-23

Mar-23

Mar-24

Dec-23

Mar-23

Mar-24

Dec-23

Mar-23

Mar-24

Dec-23

Mar-23

 

AFRICA Joint Ventures

 

76

 

93

 

64

 

509

 

478

 

538

 

416

 

433

 

342

 

 

 

 

0.97

 

1.72

 

1.32

 

4.48

 

4.76

 

3.71

 

 

 

 

2.55

 

3.17

 

2.25

Kibali - Attributable 45% (1)

76

93

64

509

478

538

416

433

342

0.97

1.72

1.32

4.48

4.76

3.71

2.55

3.17

2.25

 

AFRICA Subsidiaries

 

271

 

338

 

284

 

3,972

 

4,924

 

4,138

 

902

 

1,118

 

784

 

50

 

87

 

38

 

1.07

 

1.15

 

1.24

 

4.59

 

4.24

 

4.68

 

1.05

 

1.15

 

1.05

 

1.71

 

1.72

 

1.78

Iduapriem

62

79

63

1,273

1,516

1,233

1.53

1.61

1.58

1.53

1.61

1.58

Obuasi

54

61

60

273

286

235

50

87

38

5.91

6.30

7.74

1.05

1.15

1.05

5.15

5.10

6.81

Siguiri - Attributable 85%

41

56

63

2,084

2,700

2,324

0.61

0.65

0.86

0.61

0.65

0.86

Geita

114

142

98

615

708

581

629

832

549

1.65

2.10

2.06

4.02

3.53

3.38

2.85

2.87

2.70

 

AUSTRALIA

 

109

 

158

 

125

 

1,449

 

1,616

 

1,716

 

892

 

1,002

 

890

 

 

 

 

0.83

 

1.64

 

0.93

 

2.45

 

2.24

 

2.59

 

 

 

 

1.45

 

1.87

 

1.50

Sunrise Dam

56

62

61

325

377

349

648

631

603

0.98

1.25

1.27

2.19

2.31

2.44

1.78

1.91

2.01

Tropicana - Attributable 70%

53

96

64

1,124

1,239

1,367

244

371

287

0.79

1.76

0.84

3.14

2.13

2.91

1.21

1.85

1.20

 

AMERICAS (2)

 

125

 

136

 

99

 

187

 

201

 

211

 

422

 

476

 

430

 

676

 

772

 

597

 

1.86

 

2.24

 

2.10

 

4.53

 

4.45

 

3.87

 

2.41

 

2.15

 

1.61

 

3.03

 

2.92

 

2.48

Cerro Vanguardia - Attributable 92.50%

39

38

42

187

178

205

90

125

85

434

432

406

1.86

2.35

2.13

6.96

5.04

8.03

0.57

0.32

0.46

1.71

1.62

1.87

AngloGold Ashanti Mineração (2) (3)

65

73

42

117

84

109

242

340

191

5.50

9.00

4.70

5.72

4.47

4.05

5.65

5.37

4.29

Serra Grande

21

25

15

23

6

215

267

236

1.39

1.07

2.98

2.74

1.99

2.98

2.63

1.97

 

Subsidiaries (2)

505

632

508

5,608

6,741

6,065

2,216

2,596

2,104

726

859

635

1.03

1.30

1.18

3.72

3.51

3.63

2.32

2.05

1.58

1.84

1.93

1.80

Joint Ventures

76

93

64

509

478

538

416

433

342

0.97

1.72

1.32

4.48

4.76

3.71

2.55

3.17

2.25

Total including equity-accounted joint ventures (2)

581

725

572

6,117

7,219

6,603

2,632

3,029

2,446

726

859

635

1.03

1.33

1.19

3.84

3.69

3.64

2.32

2.05

1.58

1.91

2.03

1.84

(1)

 

Equity-accounted joint venture.

(2)

 

Adjusted to exclude the Córrego do Sítio (CdS) operation that was placed on care and maintenance in August 2023. CdS produced nil koz, 2koz and 12koz for the quarters ended 31 March 2024, 31 December 2023 and 31 March 2023, respectively.

(3)

 

Includes gold concentrate from the Cuiabá mine sold to third parties. Rounding of figures may result in computational discrepancies.

Administration and corporate information

AngloGold Ashanti plc

Incorporated in England & Wales

Registration No. 14654651

LEI No. 2138005YDSA7A82RNU96

Share codes:

ISIN: GB00BRXH2664

CUSIP: G0378L100

NYSE: AU

JSE: ANG

A2X: ANG

GhSE (Shares): AGA

GhSE (GhDS): AAD

JSE Sponsor:

The Standard Bank of South Africa Limited

Auditors: PricewaterhouseCoopers Inc.

Offices

Registered and Corporate

4th Floor, Communications House

South Street

Staines-upon-Thames

Surrey TW18 4PR

United Kingdom

Telephone: +44 (0) 203 968 3320

Fax: +44 (0) 203 968 3325

Australia

Level 10, AMP Building

140 St George’s Terrace

Perth, WA 6000

(PO Box Z5046, Perth WA 6831)

Australia

Telephone: +61 8 9425 4602

Fax: +61 8 9425 4662

Ghana

Gold House

Patrice Lumumba Road

(PO Box 2665)

Accra

Ghana

Telephone: +233 303 773400

Fax: +233 303 778155

Directors

Executive

A Calderon (Chief Executive Officer)

GA Doran (Chief Financial Officer)

Non-Executive

MDC Ramos^ (Chairman)

KOF Busia

AM Ferguson*

AH Garner#

R Gasant^

SP Lawson#

J Magie§

MC Richter#~

DL Sands#

JE Tilk§

* British § Canadian #American Australian

~Panamanian ^South African Ghanaian

Officers

C Stead

Company Secretary

Company secretarial e-mail

Companysecretary@anglogoldashanti.com

AngloGold Ashanti website

www.anglogoldashanti.com

Share Registrars

United States

Computershare Trust Company, N.A.

150 Royall Street

Suite 101

Canton, MA 02021

United States of America

Telephone US: 866-644-4127

Telephone non-US: +1-781-575-2000

Shareholder Online Inquiries:

https://www-us.computershare.com/Investor/#Contact

Website: www.computershare.com/investor

South Africa

Computershare Investor Services (Pty) Limited

Rosebank Towers, 15 Biermann Avenue

Rosebank, 2196

(PO Box 61051, Marshalltown 2107)

South Africa

Telephone: 0861 100 950 (in SA)

Fax: +27 11 688 5218

E-mail: queries@computershare.co.za

Website: www.computershare.com

Ghana

Central Securities Depository (GH) LTD

4th Floor, Cedi House

PMB CT 465, Cantonments

Accra, Ghana

Telephone: +233 302 689313

Fax: +233 302 689315

Ghana depositary

NTHC Limited

18 Gamel Abdul Nasser Avenue

Ringway Estate

Accra, Ghana

Telephone: +233 302 235814/6

Fax: +233 302 229975

AngloGold Ashanti posts information that may be important to investors on the main page of its website at www.anglogoldashanti.com and under the “Investors” tab on the main page. This information is updated periodically. AngloGold Ashanti intends to use its website as a means of disclosing material non-public information to the public in a broad, non-exclusionary manner and for complying with its disclosure obligations. Accordingly, investors should visit this website regularly to obtain important information about AngloGold Ashanti, in addition to following its press releases, documents it files with, or furnishes to, the United States Securities and Exchange Commission (SEC) and public conference calls and webcasts. No material on the AngloGold Ashanti website forms any part of, or is incorporated by reference into, this document. References herein to the AngloGold Ashanti website shall not be deemed to cause such incorporation.

PUBLISHED BY ANGLOGOLD ASHANTI

Forward-looking statements

Certain statements contained in this document, other than statements of historical fact, including, without limitation, those concerning the economic outlook for the gold mining industry, expectations regarding gold prices, production, total cash costs, all-in sustaining costs, all-in costs, cost savings and other operating results, return on equity, productivity improvements, growth prospects and outlook of AngloGold Ashanti’s operations, individually or in the aggregate, including the achievement of project milestones, commencement and completion of commercial operations of certain of AngloGold Ashanti’s exploration and production projects and the completion of acquisitions, dispositions or joint venture transactions, AngloGold Ashanti’s liquidity and capital resources and capital expenditures, the consequences of the COVID-19 pandemic and the outcome and consequences of any potential or pending litigation or regulatory proceedings or environmental, health and safety issues, are forward-looking statements regarding AngloGold Ashanti’s financial reports, operations, economic performance and financial condition. These forward-looking statements or forecasts are not based on historical facts, but rather reflect our current beliefs and expectations concerning future events and generally may be identified by the use of forward-looking words, phrases and expressions such as “believe”, “expect”, “aim”, “anticipate”, “intend”, “foresee”, “forecast”, “predict”, “project”, “estimate”, “likely”, “may”, “might”, “could”, “should”, “would”, “seek”, “plan”, “scheduled”, “possible”, “continue”, “potential”, “outlook”, “target” or other similar words, phrases, and expressions; provided that the absence thereof does not mean that a statement is not forward-looking. Similarly, statements that describe our objectives, plans or goals are or may be forward-looking statements. These forward-looking statements or forecasts involve known and unknown risks, uncertainties and other factors that may cause AngloGold Ashanti’s actual results, performance, actions or achievements to differ materially from the anticipated results, performance, actions or achievements expressed or implied in these forward-looking statements. Although AngloGold Ashanti believes that the expectations reflected in such forward-looking statements and forecasts are reasonable, no assurance can be given that such expectations will prove to have been correct. Accordingly, results, performance, actions or achievements could differ materially from those set out in the forward-looking statements as a result of, among other factors, changes in economic, social, political and market conditions, including related to inflation or international conflicts, the success of business and operating initiatives, changes in the regulatory environment and other government actions, including environmental approvals, fluctuations in gold prices and exchange rates, the outcome of pending or future litigation proceedings, any supply chain disruptions, any public health crises, pandemics or epidemics (including the COVID-19 pandemic), the failure to maintain effective internal control over financial reporting or effective disclosure controls and procedures, the inability to remediate one or more material weaknesses, or the discovery of additional material weaknesses, in the Company’s internal control over financial reporting, and other business and operational risks and challenges and other factors, including mining accidents. For a discussion of such risk factors, refer to AngloGold Ashanti’s annual report on Form 20-F for the year ended 31 December 2023 filed with the United States Securities and Exchange Commission (SEC). These factors are not necessarily all of the important factors that could cause AngloGold Ashanti’s actual results, performance, actions or achievements to differ materially from those expressed in any forward-looking statements. Other unknown or unpredictable factors could also have material adverse effects on AngloGold Ashanti’s future results, performance, actions or achievements. Consequently, readers are cautioned not to place undue reliance on forward-looking statements. AngloGold Ashanti undertakes no obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after the date hereof or to reflect the occurrence of unanticipated events, except to the extent required by applicable law. All subsequent written or oral forward-looking statements attributable to AngloGold Ashanti or any person acting on its behalf are qualified by the cautionary statements herein.

Non-GAAP financial measures

This communication may contain certain “Non-GAAP” financial measures. AngloGold Ashanti utilises certain Non-GAAP performance measures and ratios in managing its business. Non-GAAP financial measures should be viewed in addition to, and not as an alternative for, the reported operating results or cash flow from operations or any other measures of performance prepared in accordance with IFRS. In addition, the presentation of these measures may not be comparable to similarly titled measures other companies may use.

Contacts

Data & News supplied by www.cloudquote.io
Stock quotes supplied by Barchart
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms and Conditions.
 
 
Copyright © 2010-2020 CorteMadera.com & California Media Partners, LLC. All rights reserved.